Major Work Activity E - Performs exterior finishing
Table of Contents
- Task E-14 Installs exterior doors and windows
- Task E-15 Installs roofing
- Task E-16 Installs exterior finishes
Task E-14 Installs exterior doors and windows
Task Descriptor
Carpenters install exterior doors and windows to ensure energy efficient construction. This is essential to maintain the integrity of the building envelope.
E-14.01 - Installs exterior jambs/frames
NL | NS | PE | NB | QC | ON | MB | SK | AB | BC | NT | YT | NU |
---|---|---|---|---|---|---|---|---|---|---|---|---|
yes | yes | NV | yes | NV | yes | yes | yes | yes | yes | NV | NV | NV |
Reference Code | Performance Criteria | Evidence of Attainment |
---|---|---|
E-14.01.01P | select and use tools and equipment | tools and equipment are selected and used according to project requirements and manufacturers’ specifications |
E-14.01.02P | select frames for openings | frames for openings are selected according to schedule, drawings and specifications |
E-14.01.03P | assess and adjust rough openings | rough openings are assessed and adjusted for pre-existing conditions |
E-14.01.04P | prepare hinges and bolt locations on metal door frames | hinges and bolt locations on metal door frames are prepared to protect from grout and mortar |
E-14.01.05P | brace metal door frames | metal door frames are braced for plumb, square and support |
E-14.01.06P | align adjacent jambs/frames | adjacent jambs/frames are aligned with each other |
E-14.01.07P | level head jamb and plumb side jambs | head jamb is level and side jambs are plumb |
E-14.01.08P | secure jambs/frames | jambs/frames are secured by shimming and fastening to steel, wood and masonry |
E-14.01.09P | insulate cavity around jambs/frames | cavity around jambs/frames is insulated to create a thermal break according to codes and project requirements |
E-14.01.10P | coordinate with other trades | other trades are coordinated with to ensure considerations are made for components and exterior door and window hardware |
E-14.01.11P | install membrane and flashing around outside exterior jamb’s trim | membrane and flashing is installed around outside exterior jamb’s trim according to codes and project requirements |
Range of Variables
- tools and equipment include: see Appendix B
- drawingsinclude: project, shop, engineering, architectural, structural
- specificationsinclude: project, engineer, manufacturers’
- pre-existing conditions include: out-of-square, out-of-level, wrong size, wrong location, wood rot
- exterior door and window hardware include: locks, latches, electronic systems, astragals, kick plates, stops, hinges, closers
Reference Code | Learning Outcomes | Learning Objectives |
---|---|---|
E-14.01.01L | demonstrate knowledge of exterior jambs and frames, their characteristics and applications | identify types of exterior window and door jambs/frames, and describe their characteristics and applications |
identify types of exterior doors and windows, and describe their characteristics and applications | ||
identify exterior door components, and describe their characteristics and applications | ||
identify weather protection systems, and describe their characteristics and applications | ||
identify air and vapour barriers, and describe their characteristics and applications | ||
identify types of exterior door and window hardware, and describe their characteristics and applications | ||
identify exterior door and window schedules, and describe their characteristics and applications | ||
describe barrier-free access requirements | ||
E-14.01.02L | demonstrate knowledge of procedures to install exterior jambs/frames | identify tools and equipment used to install exterior jambs/frames, and describe their procedures for use |
describe procedures to install exterior jambs/frames | ||
E-14.01.03L | demonstrate knowledge of regulatory requirements for installing exterior jambs/frames | identify standards and regulations for installing exterior jambs/frames |
Range of Variables
- components include: side jambs, head jambs, sill, threshold, exterior finishes, flooring, access hardware, alarm system, security hardware
- weather protection systems include: flashing, weather stripping, sealants, membranes
- exterior door and window hardware include: locks, latches, electronic systems, astragals, kick plates, stops, hinges, closers
- tools and equipment include: see Appendix B
- standards and regulations include: CSA, OH&S, building codes (NBC, local), site-specific (company or client), jurisdictional requirements
E-14.02 - Installs exterior doors
NL | NS | PE | NB | QC | ON | MB | SK | AB | BC | NT | YT | NU |
---|---|---|---|---|---|---|---|---|---|---|---|---|
yes | yes | NV | yes | NV | yes | yes | yes | yes | yes | NV | NV | NV |
Reference Code | Performance Criteria | Evidence of Attainment |
---|---|---|
E-14.02.01P | select and use tools and equipment | tools and equipment are selected and used according to project requirements and manufacturers’ specifications |
E-14.02.02P | select door type and exterior door components | door type and exterior door components are selected according to door schedule, drawings and specifications |
E-14.02.03P | determine swing for pedestrian doors | swing is determined for pedestrian doors according to door schedule, codes, drawings and project requirements |
E-14.02.04P | mark door slab and jamb for hinge location | door slab and jamb are marked for hinge location according to jamb or door type and project requirements |
E-14.02.05P | mortise hinge gains on slab and jambs | hinge gains are mortised on slab and jambs according to jamb or door type and project requirements |
E-14.02.06P | secure door to jamb using fasteners | door is secured to jamb using fasteners according to manufacturers’ specifications |
E-14.02.07P | install weather protection systems | weather protection systems are installed according to manufacturers’ specifications, door hardware schedule and project requirements |
E-14.02.08P | install door accessories | door accessories are installed according to manufacturers’ specifications, door hardware schedule and project requirements |
E-14.02.09P | coordinate with other trades | other trades are coordinated with to ensure considerations are made for exterior door components and hardware |
E-14.02.10P | verify operation | operation is verified according to codes and project requirements |
Range of Variables
- tools and equipment include: see Appendix B
- door type includes: overhead, access hatch, bypass, panel, flush, security, fire rated
- exterior door components include: rails, stiles, panels, lites, exterior finishes, flooring, access hardware, alarm system, security hardware
- drawings include: project, shop, engineering, electrical, architectural, mechanical, structural, site plans
- specificationsinclude: project, engineer, manufacturers’
- fasteners include: wood screws, metal screws, bolts, lag screws, anchors
- weather protection systems include: flashing, weather stripping, sealants, membranes
- door accessories include: astragals, kick plates, stops,hinges, closers
- exterior door hardware include: locks, latches, electronic systems, astragals, kick plates, stops,hinges, closers
- operation include: latching, spacing, alignment, clearances
Reference Code | Learning Outcomes | Learning Objectives |
---|---|---|
E-14.02.01L | demonstrate knowledge of exterior doors, their characteristics and applications | identify exterior door types, and describe their characteristics and applications |
identify types of fasteners, and describe their characteristics and applications | ||
identify types of membranes and flashings, and describe their characteristics and applications | ||
identify types of door jambs/frames, and describe their characteristics and applications | ||
identify exterior door components, and describe their characteristics and applications | ||
identify door accessories, and describe their characteristics and applications | ||
identify weather protection systems, and describe their characteristics and applications | ||
identify air and vapour barriers, and describe their characteristics and applications | ||
identify types and styles of exterior door hardware, and describe their characteristics and applications | ||
identify exterior door schedules, and describe their characteristics and applications | ||
describe barrier-free access requirements | ||
E-14.02.02L | demonstrate knowledge of procedures to install exterior doors | identify tools and equipment used to install exterior doors, and describe their procedures for use |
describe procedures to install exterior doors | ||
E-14.02.03L | demonstrate knowledge of training and certification requirements for installing exterior doors | identify training and certification requirements for installing exterior doors and specialty hardware (security) |
E-14.02.04L | demonstrate knowledge of regulatory requirements for installing exterior doors | identify standards and regulations for installing exterior doors |
Range of Variables
- door type includes: overhead, access hatch, bypass, panel, flush, security, fire rated
- fasteners include: wood screws, metal screws, bolts, lag screws, anchors
- exterior door components include: rails, stiles, panels, lites, exterior finishes, flooring, access hardware, alarm system, security hardware
- door accessories include: astragals, kick plates, stops, hinges, closers
- weather protection systems include: flashing, weather stripping, sealants, membranes
- exterior door hardware include: locks, latches, electronic systems, astragals, kick plates, stops,hinges, closers
- tools and equipment include: see Appendix B
- standards and regulations include: CSA, OH&S, building codes (NBC, local), site-specific (company or client), jurisdictional requirements
E-14.03 - Installs exterior windows
NL | NS | PE | NB | QC | ON | MB | SK | AB | BC | NT | YT | NU |
---|---|---|---|---|---|---|---|---|---|---|---|---|
yes | yes | NV | yes | NV | yes | yes | yes | yes | yes | NV | NV | NV |
Reference Code | Performance Criteria | Evidence of Attainment |
---|---|---|
E-14.03.01P | select and use tools and equipment | tools and equipment are selected and used according to project requirements and manufacturers’ specifications |
E-14.03.02P | select windows | windows are selected according to window schedule, codes and project requirements |
E-14.03.03P | assess and adjust rough openings | rough openings are assessed and adjusted for pre-existing conditions |
E-14.03.04P | place and secure window in rough opening | window is placed and secured in rough opening using shims and fasteners to level and plumb |
E-14.03.05P | brace window frames | window frames are braced for plumb, square and support |
E-14.03.06P | align adjacent jambs/frames | adjacent jambs/frames are aligned with each other and other units according to project requirements |
E-14.03.07P | install weather protection systems | weather protection systems are installed according to codes, drawings, specifications, window hardware schedule and project requirements |
E-14.03.08P | coordinate with other trades | other trades are coordinated with to ensure considerations are made for components |
E-14.03.09P | verify operation | operation is verified according to codes and project requirements |
Range of Variables
- tools and equipment include: see Appendix B
- pre-existing conditions include: out-of-square, out-of-level and wrong size, wrong location, wood rot
- weather protection systems include: flashing, weather stripping, sealants, membranes
- drawings include: project, shop, engineering, electrical, architectural, mechanical, structural, site plans
- specifications include: project, engineer, manufacturers’
- components include: exterior finishes, access hardware, alarm system, security hardware
- operation includes: latching, spacing, alignment, clearances
Reference Code | Learning Outcomes | Learning Objectives |
---|---|---|
E-14.03.01L | demonstrate knowledge of exterior windows, their characteristics and applications | identify types of exterior windows, and describe their characteristics and applications including their energy efficiency |
identify types of window jambs/frames, and describe their characteristics and applications | ||
identify exterior window components, and describe their characteristics and applications | ||
identify weather protection systems, and describe their characteristics and applications | ||
identify air and vapour barriers, and describe their characteristics and applications | ||
identify types and styles of exterior window hardware, and describe their characteristics and applications | ||
identify exterior window schedules, and describe their characteristics and applications | ||
describe egress requirements | ||
E-14.03.02L | demonstrate knowledge of procedures to install exterior windows | identify tools and equipment used to install exterior windows, and describe their procedures for use |
describe procedures to install exterior windows | ||
E-14.03.03L | demonstrate knowledge of regulatory requirements for installing exterior windows | identify standards and regulations for installing exterior windows |
Range of Variables
- energy efficiency includes: gas filled, reflective coatings
- exterior window components include: stiles, rails, mullions, muttons
- weather protection systems include: flashing, weather stripping, sealants, membranes
- exterior window hardware include: locks, latches, electronic systems
- tools and equipment include: see Appendix B
- standards and regulations include: CSA, OH&S, building codes (NBC, local), site-specific (company or client), jurisdictional requirements
E-14.04 - Installs exterior door and window hardware
NL | NS | PE | NB | QC | ON | MB | SK | AB | BC | NT | YT | NU |
---|---|---|---|---|---|---|---|---|---|---|---|---|
yes | yes | NV | yes | NV | yes | yes | yes | yes | yes | NV | NV | NV |
Reference Code | Performance Criteria | Evidence of Attainment |
---|---|---|
E-14.04.01P | select and use tools and equipment | tools and equipment are selected and used according to project requirements and manufacturers’ specifications |
E-14.04.02P | select exterior door and window hardware | exterior door and window hardware is selected according to specifications, codes, and door and window hardware schedule |
E-14.04.03P | position exterior door and window hardware | exterior door and window hardware is positioned using layout tools according to specifications, codes and project requirements |
E-14.04.04P | secure exterior door and window hardware | exterior door and window hardware is secured to door or window according to specifications |
E-14.04.05P | adjust exterior door and window hardware | exterior door and window hardware is adjusted to ensure smooth operation |
E-14.04.06P | coordinate with other trades | other trades are coordinated with to ensure considerations are made for components |
E-14.04.07P | verify operation | operation is verified according to codes and project requirements |
Range of Variables
- tools and equipment include: see Appendix B
- exterior door and window hardware include: locks, latches, electronic systems, closers, emergency devices, panic hardware
- specifications include: project, engineer, manufacturers’
- layout tools include: templates, mortising jigs, manufacturers’ templates
- considerations include: exterior finishes, flooring, access hardware, alarm system, security hardware
- operation includes: latching, spacing, alignment, clearances
Reference Code | Learning Outcomes | Learning Objectives |
---|---|---|
E-14.04.01L | demonstrate knowledge of exterior door and window hardware, their characteristics and applications | identify types of exterior door and window hardware, and describe their characteristics and applications |
identify types of window and door jambs/frames, and describe their characteristics and applications | ||
identify types of exterior doors and windows, and describe their characteristics and applications | ||
identify exterior door and window components, and describe their characteristics and applications | ||
identify weather protection systems, and describe their characteristics and applications | ||
identify exterior door and window schedules, and describe their characteristics and applications | ||
describe barrier-free access requirements | ||
describe egress requirements | ||
identify sound transmission control methods and fire ratings, and describe their characteristics and applications | ||
E-14.04.02L | demonstrate knowledge of procedures to install exterior door and window hardware | identify tools and equipment used to install exterior door and window hardware, and describe their procedures for use |
describe procedures to install exterior door and window hardware | ||
describe procedures to position hardware using layout tools | ||
E-14.04.03L | demonstrate knowledge of training and certification requirements for installing exterior door and window hardware | identify training and certification requirements for installing exterior door, window and specialty hardware (security) |
E-14.04.04L | demonstrate knowledge of regulatory requirements for installing exterior door and window hardware | identify standards and regulations for installing exterior door and window hardware |
Range of Variables
- exterior door and window hardware include: locks, latches, electronic systems, closers, emergency devices, panic hardware
- exterior door and window components include: transom, mullion, astragal, muntin, sash
- weather protection systems include: flashing, weather stripping, sealants, membranes
- sound transmission control methods include: cores, weather stripping, frame grouting
- tools and equipment include: see Appendix B
- layout tools include: templates, mortising jigs, manufacturers’ templates
- standards and regulations include: CSA, OH&S, building codes (NBC, local), site-specific (company or client), jurisdictional requirements
Task E-15 Installs roofing
Task Descriptor
Carpenters install roofing for the purpose of protecting the building from the elements as well as functionality and aesthetics. Proper installation methods are critical to maintaining the building envelope.
E-15.01 - Installs roofing components
NL | NS | PE | NB | QC | ON | MB | SK | AB | BC | NT | YT | NU |
---|---|---|---|---|---|---|---|---|---|---|---|---|
yes | yes | NV | yes | NV | yes | yes | yes | yes | yes | NV | NV | NV |
Reference Code | Performance Criteria | Evidence of Attainment |
---|---|---|
E-15.01.01P | select and use tools and equipment | tools and equipment are selected and used according to project requirements and manufacturers’ specifications |
E-15.01.02P | select roof ventilation components | roof ventilation components are selected according to location, standards and regulations, and type and size of roof |
E-15.01.03P | assess and adjust roofing components | roofing components are assessed and adjusted for pre-existing conditions |
E-15.01.04P | select strapping | strapping is selected according to specifications and product requirements |
E-15.01.05P | select flashing | flashing is selected according to location, specifications and type of roof |
E-15.01.06P | apply membrane | membrane materials are applied according to codes and specifications |
E-15.01.07P | apply flashing | flashing is applied to direct water and prevent moisture penetration using fasteners and sealants according to specifications |
E-15.01.08P | mount roof ventilation components | roof ventilation components are mounted according to codes and specifications |
E-15.01.09P | install skylights | skylights are installed according to specifications |
E-15.01.10P | install roof safety components | roof safety components are installed according to codes, specifications, and regulations |
E-15.01.11P | select fasteners and sealants | fasteners and sealants are selected according to specifications |
E-15.01.12P | apply fasteners and sealants | fasteners and sealants are applied according to specifications |
Range of Variables
- tools and equipment include: see Appendix B
- roof ventilation components include: ridge vents, exhaust vents
- standards and regulations include: CSA, OH&S, building codes (NBC, local), site-specific (company or client), jurisdictional requirements
- specifications include: project, engineer, manufacturers’
- flashing includes: drip edges, step flashing, cap flashing, valley flashing, saddle flashing, vent and chimney flashing, neoprene roof flashing
- membrane includes: rolled roofing, ice and water shield, synthetic felt, tar paper
- roof safety components include: anchors, davit systems
Reference Code | Learning Outcomes | Learning Objectives |
---|---|---|
E-15.01.01L | demonstrate knowledge of roofing components, their characteristics and applications | identify types of strapping, their characteristics and applications |
identify types of membranes, their characteristics and applications | ||
identify types of flashing, their characteristics and applications | ||
identify types of sealants, their characteristics and applications | ||
identify types of roof ventilation components, their characteristics and applications | ||
describe types of fasteners, their characteristics and applications | ||
describe adhesion requirements for site conditions | ||
describe sequence of installation | ||
describe safety requirements | ||
describe handling and placement requirements for roofing materials | ||
E-15.01.02L | demonstrate knowledge of procedures to install roofing components | identify tools and equipment used to install roofing components, and describe their procedures for use |
identify substrate requirements | ||
describe procedures to install strapping | ||
describe procedures to install membranes | ||
describe procedures to install flashing | ||
describe procedures to install sealants | ||
describe procedures to install roof ventilation components | ||
describe procedures to repair roofing components | ||
E-15.01.03L | demonstrate knowledge of training and certification requirements for installing roofing components | identify training and certification requirements for installing roofing components |
E-15.01.04L | demonstrate knowledge of regulatory requirements for installing roofing components | identify standards and regulations for installing roofing components |
Range of Variables
- membrane includes: rolled roofing, ice and water shield, synthetic felt, tar paper
- flashing includes: drip edges, step flashing, cap flashing, valley flashing, saddle flashing, vent and chimney flashing, neoprene roof flashing
- roof ventilation components include: ridge vents, exhaust vents
- safety requirements include: fall protection, fire protection
- tools and equipment include: see Appendix B
- standards and regulations include: CSA, OH&S, building codes (NBC, local), site-specific (company or client), jurisdictional requirements
E-15.02 - Installs roof coverings
NL | NS | PE | NB | QC | ON | MB | SK | AB | BC | NT | YT | NU |
---|---|---|---|---|---|---|---|---|---|---|---|---|
yes | yes | NV | yes | NV | yes | yes | yes | yes | yes | NV | NV | NV |
Reference Code | Performance Criteria | Evidence of Attainment |
---|---|---|
E-15.02.01P | select and use tools and equipment | tools and equipment are selected and used according to project requirements and manufacturers’ specifications |
E-15.02.02P | select roofing materials | roofing materials are selected according to site requirements, conditions, standards and regulations, and specifications |
E-15.02.03P | secure metal roofing materials | metal roofing materials are secured according to standards and regulations, and specifications |
E-15.02.04P | secure wood roofing materials | wood roofing materials are secured according to standards and regulations, and specifications |
E-15.02.05P | secure asphalt composite roofing materials | asphalt composite roofing materials are secured according to standards and regulations, and specifications |
E-15.02.06P | install ridge and hip caps | ridge and hip caps are installed according to specifications |
Range of Variables
- tools and equipment include: see Appendix B
- roofing materials include: asphalt composite, wood, metal, synthetic, clay, slate
- standards and regulations include: CSA, OH&S, building codes (NBC, local), site-specific (company or client), jurisdictional requirements
- specifications include: project, engineer, manufacturers’
- metal roofing materials include: corrugated, steel tile
- wood roofing materials include: shakes, shingles
- asphalt composite roofing materials include: shingles, rolled roofing, ballast, selvage, granular, smooth bitumen, torch-down, fibreglass
Reference Code | Learning Outcomes | Learning Objectives |
---|---|---|
E-15.02.01L | demonstrate knowledge of roof coverings, their characteristics and applications | identify types of roofing materials, and describe their characteristics and applications |
identify types of metal roofing materials, and describe their characteristics and applications | ||
identify types of wood roofing materials, and describe their characteristics and applications | ||
identify types of asphalt composite roofing materials, and describe their characteristics and applications | ||
identify types of fasteners, and describe their characteristics and applications | ||
describe adhesion requirements for site conditions | ||
describe sequence of installation | ||
identify safety requirements | ||
describe handling and placement requirements for roofing materials | ||
E-15.02.02L | demonstrate knowledge of procedures to install roofing materials | identify tools and equipment used to install roofing materials, and describe their procedures for use |
describe procedures to install roofing materials | ||
E-15.02.03L | demonstrate knowledge of regulatory requirements for installing roofing materials | identify standards and regulations for installing roofing materials |
Range of Variables
- roofing materials include: asphalt composite, wood, metal, synthetic, clay, slate
- metal roofing materials include: corrugated, steel tile
- wood roofing materials include: shakes, shingles
- asphalt composite roofing materials include: shingles, rolled roofing, ballast, selvage, granular, smooth bitumen, torch-down, fibreglass
- tools and equipment include: see Appendix B
- standards and regulations include: CSA, OH&S, building codes (NBC, local), site-specific (company or client), jurisdictional requirements
Task E-16 Installs exterior finishes
Task Descriptor
The installation of exterior finishes is essential to the aesthetics, comfort, weather protection and functioning of the building. Carpenters install exterior finishes for aesthetics, comfort, weather protection and functioning of the building. Different components work together effectively to create a weather shield while contributing to the curb appeal of the structure.
E-16.01 - Installs exterior wall components
NL | NS | PE | NB | QC | ON | MB | SK | AB | BC | NT | YT | NU |
---|---|---|---|---|---|---|---|---|---|---|---|---|
yes | yes | NV | yes | NV | yes | yes | yes | yes | yes | NV | NV | NV |
Reference Code | Performance Criteria | Evidence of Attainment |
---|---|---|
E-16.01.01P | select and use tools and equipment | tools and equipment are selected and used according to project requirements and manufacturers’ specifications |
E-16.01.02P | check for plumb, level and square structure | structure is checked for plumb, level and square and exterior wall coverings are adjusted for aesthetics |
E-16.01.03P | select and install membranes, adhesives and sealants | membranes, adhesives and sealants are selected and installed according to specifications and exterior wall coverings |
E-16.01.04P | select and install flashings | flashings are selected and installed according to specifications, building codes and exterior wall coverings |
E-16.01.05P | select and install strapping | strapping is selected and installed according to specifications and exterior wall coverings |
E-16.01.06P | select and install cladding components | cladding components are selected and installed according to specifications and exterior wall coverings |
E-16.01.07P | select and install fasteners | fasteners are selected and installed according to specifications and exterior wall coverings |
E-16.01.08P | select and install coverings for cornice (soffit/fascia) | coverings for cornice (soffit/fascia) are selected and installed according to specifications |
Range of Variables
- tools and equipment include: see Appendix B
- exterior wall coverings include: wood, vinyl, composite products, masonry, stucco
- membranes, adhesives and sealants include: air barriers, tar paper, self-adhesive membrane, weather barrier, sheathing tape, silicone, latex and acrylic caulking
- flashings include: window flashing, door flashing, sills, transition flashing
- strapping includes: z-bar, furring, ventilated underlayment, lattice work
- cladding components include: starter strips, trims, corner posts, frieze boards, water table, belt course
- fasteners include: electro‑galvanized nails, stainless steel nails, ring nails, coated screws, specialty fasteners
Reference Code | Learning Outcomes | Learning Objectives |
---|---|---|
E-16.01.01L | demonstrate knowledge of exterior wall components, their characteristics, applications and procedures for use | identify membranes, adhesives and sealants, and describe their characteristics, applications and procedures for use |
identify flashings, and describe their characteristics, applications and procedures for use | ||
identify strapping, and describetheir characteristics, applications and procedures for use | ||
identify cladding components, and describe their characteristics, applications and procedures for use | ||
identify fasteners, and describe their characteristics, applications and procedures for use | ||
identify exterior wall coverings, and describe their characteristics, applications and procedures for use | ||
identify planes of protection and rain screen, and describe their characteristics and applications | ||
E-16.01.02L | demonstrate knowledge of remedial measures for out-of-plumb, not level or not square structure | describe remedial measures for out-of-plumb, not level or not square structure |
E-16.01.03L | demonstrate knowledge of coverings for cornice (soffit/fascia), and their procedures for use | identify coverings for cornice (soffit/fascia) their characteristics and applications |
E-16.01.04L | demonstrate knowledge of procedures to install exterior wall components | describe procedures to install membranes, adhesives and sealants |
describe procedures to install flashings | ||
describe procedures to install strapping | ||
describe procedures to install cladding components | ||
describe procedures to install fasteners | ||
describe sequence of installation |
Range of Variables
- membranes, adhesives and sealants include: air barriers, tar paper, self-adhesive membranes, weather barrier, sheathing tape, silicone, latex and acrylic caulking
- flashings include: window flashing, door flashing, sills, transition flashing
- strapping includes: z-bar, furring, ventilated underlayment, lattice work
- cladding components include: starter strips, trims, corner posts, frieze boards, water table, belt course
- fasteners include: electro‑galvanized nails, stainless steel nails, ring nails, coated screws, specialty fasteners
- exterior wall coverings include: wood, vinyl, composite products, masonry, stucco
E-16.02 - Installs exterior wall coverings
NL | NS | PE | NB | QC | ON | MB | SK | AB | BC | NT | YT | NU |
---|---|---|---|---|---|---|---|---|---|---|---|---|
yes | yes | NV | yes | NV | yes | yes | yes | yes | yes | NV | NV | NV |
Reference Code | Performance Criteria | Evidence of Attainment |
---|---|---|
E-16.02.01P | select and use tools and equipment | tools and equipment are selected and used according to project requirements and manufacturers’ specifications |
E-16.02.02P | select exterior wall coverings | exterior wall coverings are selected according to specifications |
E-16.02.03P | apply exterior wall coverings | exterior wall coverings are applied for desired aesthetics and weather protection according to specifications |
E-16.02.04P | prepare joints | joints are prepared according to exterior wall coverings being installed, and specifications |
Range of Variables
- tools and equipment include: see Appendix B
- exterior wall coverings include: wood, vinyl, composite products, masonry, stucco, rain screens, steel
- specifications include: project, engineer, manufacturers’
- joints include: butt, scarf, mitre, lap, control
Reference Code | Learning Outcomes | Learning Objectives |
---|---|---|
E-16.02.01L | demonstrate knowledge of exterior wall coverings, their characteristics and applications | identify types of exterior wall coverings, and describe their characteristics and applications |
describe effects of weather on exterior walls and exterior wall coverings | ||
describe installation sequence and procedures for exterior wall coverings | ||
identify types of fasteners, and describe their characteristics and applications | ||
identify safetyrequirements | ||
identify types of joints, and describe their characteristics, applications and procedures for use | ||
E-16.02.02L | demonstrate knowledge installation of exterior wall coverings | identify tools and equipment used to install exterior wall coverings, and describe their procedures for use |
describe procedures to install exterior wall coverings | ||
describe procedures to prepare joints | ||
E-16.02.03L | demonstrate knowledge of regulatory requirements for installing exterior wall coverings | identify standards and regulations for installing exterior wall coverings |
Range of Variables
- exterior wall coverings include: wood, vinyl, composite products, masonry, stucco, rain screens, steel
- fasteners include: electro‑galvanized nails, ring nails, stainless steel nails, specialty fasteners, screws with washers
- joints include: butt, scarf, mitre, lap, control
- tools and equipment include: see Appendix B
- standards and regulations include: CSA, OH&S, building codes (NBC, local), site-specific (company or client), jurisdictional requirements