Examination Weightings
Pie Chart of Red Seal Examination Weightings

Text version
- Major Work Activity A - Performs common occupational skills 18%
- Major Work Activity B - Performs site work 20%
- Major Work Activity C - Uses scaffolding and access equipment 10%
- Major Work Activity D - Performs concrete work 19%
- Major Work Activity E - Performs masonry work 12%
- Major Work Activity F - Performs utility and pipeline work 11%
- Major Work Activity G - Performs roadwork 10%
This pie chart represents a breakdown of the interprovincial Red Seal examination. Percentages are based on the collective input from workers from the trade from across Canada. The Task Matrix on the next pages indicates the breakdown of tasks and sub-tasks within each Major Work Activity and the breakdown of questions assigned to the Tasks. The Interprovincial examination for this trade has 100 questions.
Construction Craft Worker - Task Matrix and Weightings
Major Work Activity A – Performs common occupational skills 18%
- Task A-1 Maintains safe and healthy workplace 19%
- A-1.01 Maintains safe work environment
- A-1.02 Uses personal protective equipment (PPE) and safety equipment
- A-1.03 Participates in healthy and respectful work environment
- Task A-2 Uses and maintains tools and equipment 27%
- A-2.01 Uses hand, pneumatic, power and powder-actuated tools
- A-2.02 Uses rigging and hoisting equipment
- A-2.03 Uses stationary and portable equipment
- A-2.04 Uses media blasting equipment
- A-2.05 Uses mobile equipment
- Task A-3 Organizes work 18%
- A-3.01 Uses documentation
- A-3.02 Handles construction materials
- A-3.03 Performs site housekeeping and maintenance
- Task A-4 Performs routine trade activities 30%
- A-4.01 Erects hoarding/enclosures
- A-4.02 Installs membranes
- A-4.03 Installs insulating materials
- A-4.04 Establishes grades and elevations
- A-4.05 Performs traffic control
- A-4.06 Installs permanent and temporary fencing
- Task A-5 Maintains continuous learning 3%
- A-5.01 Upskills in new trade practices and procedures
- A-5.02 Upskills in emerging technologies
- Task A-6 Uses communication and mentoring techniques 3%
- A-6.01 Uses communication techniques
- A-6.02 Uses mentoring techniques
Major Work Activity B – Performs site work 20%
- Task B-7 Prepares site 22%
- B-7.01 Clears site
- B-7.02 Sets up site facilities
- B-7.03 Assists in installation of pilings and caissons
- B-7.04 Builds access and egress roads
- Task B-8 Performs groundwork 24%
- B-8.01 Locates underground utilities
- B-8.02 Performs excavation
- B-8.03 Installs excavation shoring and shielding
- B-8.04 Performs backfill and compaction
- Task B-9 Services site 19%
- B-9.01 Addresses suspected hazardous materials
- B-9.02 Controls water runoff
- B-9.03 Sets up temporary lighting
- B-9.04 Sets up generators and compressors
- B-9.05 Performs site restoration
- B-9.06 Manages tool crib
- B-9.07 Recycles materials
- Task B-10 Performs basic demolition 18%
- B-10.01 Cuts materials
- B-10.02 Dismantles existing structures and components
- Task B-11 Performs safety watches 17%
- B-11.01 Monitors hazardous gases and atmospheres
- B-11.02 Performs fire watch
- B-11.03 Performs bottle watch
- B-11.04 Performs confined space watch
- B-11.05 Monitors heaters
Major Work Activity C – Uses scaffolding and access equipment 10%
- Task C-12 Uses scaffolding 54%
- C-12.01 Erects scaffolding
- C-12.02 Inspects scaffolding
- C-12.03 Maintains scaffolding
- C-12.04 Tends to scaffold erectors
- C-12.05 Dismantles scaffolding
- Task C-13 Uses access equipment 46%
- C-13.01 Uses ladders
- C-13.02 Uses stationary and mobile elevating work platforms (MEWP)
- C-13.03 Inspects access equipment
- C-13.04 Maintains access equipment
Major Work Activity D – Performs concrete work 19%
- Task D-14 Forms concrete 26%
- D-14.01 Installs formwork and shoring
- D-14.02 Inspects assembled formwork
- D-14.03 Dismantles formwork
- Task D-15 Places and finishes concrete 35%
- D-15.01 Mixes concrete
- D-15.02 Transports concrete on site
- D-15.03 Places concrete
- D-15.04 Installs embedded components in concrete
- D-15.05 Assists with finishing concrete
- D-15.06 Controls concrete curing process
- Task D-16 Modifies concrete 23%
- D-16.01 Drills/cores/cuts concrete
- D-16.02 Prepares concrete for resurfacing
- D-16.03 Performs concrete repair and refinishing
- D-16.04 Creates expansion, control and isolation joints
- Task D-17 Places/Applies grout, epoxies, caulking and chemical materials 16%
- D-17.01 Places/Applies grout
- D-17.02 Places/Applies epoxies and chemical materials
- D-17.03 Applies caulking
Major Work Activity E – Performs masonry work 12%
- Task E-18 Prepares for masonry work 44%
- E-18.01 Sets up masonry materials
- E-18.02 Mixes mortars and grouts
- Task E-19 Tends to bricklayers 56%
- E-19.01 Cuts masonry units
- E-19.02 Assists with installation of lintels and rough bucks
- E-19.03 Washes masonry units
- E-19.04 Installs refractory materials
- E-19.05 Uses fireproofing materials
Major Work Activity F – Performs utility and pipeline work 11%
- Task F-20 Installs piping for utilities 61%
- F-20.01 Installs pipe for water systems
- F-20.02 Installs pipe for sanitary and storm sewer systems
- F-20.03 Installs pipe for other utility infrastructure
- F-20.04 Installs catch basins, utility vaults, weeping tile and maintenance holes
- F-20.05 Modifies existing pipe
- F-20.06 Assists with testing water, sanitary and storm sewer lines
- Task F-21 Performs pipeline activities 39%
- F-21.01 Constructs right of ways
- F-21.02 Performs pipeline installation
- F-21.03 Performs pipeline maintenance
Major Work Activity G – Performs roadwork 10%
- Task G-22 Prepares and builds roads 57%
- G-22.01 Prepares earth for right of way
- G-22.02 Places layers and road surface materials for roadwork
- G-22.03 Repairs road surfaces
- Task G-23 Installs roadwork components 43%
- G-23.01 Installs barriers
- G-23.02 Installs road markings and signs
- G-23.03 Installs culverts